Anticipated Operating Costs for a 100 Tons Per Day WG/TO System
Number of PRIMARY gasification cells |
ea |
3 |
Number of SECONDARY gas processors |
ea |
1 |
Average Space Requirement |
acres |
2.5 |
Total Pilots and Igniters |
ea |
10 |
Total LPG Consumption |
gal/hr |
3.6 |
Cost per Unit of Supplemental Fuel |
$/gal |
0.43 |
Total Supplemental Fuel Cost per Day |
$ |
37.15 |
Total Air Supply Fans and Blowers |
ea |
7 |
Total KWHr for Fans |
KW-Hr |
92.4 |
Other Miscellaneous Power Use |
KW-Hr |
40 |
Total Power Consumption |
KW-Hr |
132.4 |
Cost per Unit of Electrical Power |
$/KW-Hr |
0.06 |
Total Electrical Power Cost per Day |
$ |
190.66 |
Total Daily Operator Hours Required |
Hrs. |
24 |
Operator Hourly Pay Rate ( Fully Burdened ) |
$ |
17.00 |
Total Daily Labor Hours Required |
Hrs. |
32 |
Labor Hourly Pay Rate ( Fully Burdened ) |
$ |
10.00 |
Total Payroll per Day |
$ |
728.00 |
Average Daily Misc. Expense |
$ |
45.56 |
Total Daily Operating Cost |
$ |
1,001.37 |
Total Operating Cost per Ton of Waste |
$ |
10.01 |
The amounts used to calculate this operating cost are based on costs for labor, fuel and electricity in central Kentucky for a 100 tons per day system. To find out what your operating costs would be, just fill out our Waste Survey Form. We'll be happy to provide you with a proposal designed to meet your individual needs and help eliminate your waste disposal problems!